Project Name: Hastings College – OCS Foundations
Location: Hyde St, San Francisco, CA
Owner: Hastings College
Owner Contact: N/A
Prime Contractor: Kingston Constructors, Inc.
Prime Contractor: Contact Marty Gilman
Architect/Engineer: N/A
Architect/Engineer Contact: N/A
Construction Manger Contact: N/A
Description Of Project Scope: Performed civil support work for OCS contractor which included installing (11) OCS pole foundations & the removal of 3 existing foundations. C-QC completed the work in a week.
Original Bid Amount: $ 40,000
Change Orders: $ 0
Claims: $ ---0---
Final Contract Value: $40,000
Original Start Date: April, 2009
Original Duration: N/A
Original Completion Date: April, 2009
Time Extension Granted In Days: N/A
Actual Completion Date: April, 2009
Liquidated Damages: None
Recordable Accidents/ RAF: Zero / 0
Lost Time Accidents/ LAF: Zero / 0
OSHA Violations/ Fines: None
DOWNLOAD PDF
Project Name: San Francisco Veteran Affairs Hospital
Location: San Francisco, CA
Owner: SFVA – Army Corps of Engineers
Owner Contact:
Prime Contractor: Helix Electric
Prime Contractor Contact: Brady Hill – 415.933.6196
Architect/Engineer: Winzler & Kelly
Architect/Engineer Contact: N/A
Construction Manger Contact: N/A
Description Of Project Scope: Con-Quest performed as a subcontractor providing civil support for Helix Electric to install a new electrical ductbank in order to upgrade the SFVA hospitals system. Work on this congested work site included:
- 4,000 lf of 3’ x 5’ trenching including sawcutting and offhaul of native materials for power and communication ductbank
- 7,000 lf of 18” x 2’ trenching for new site lighting
- Drill and form 44 new light pole bases
- Form and pour 7 new large equipment pads including retaining walls and inlaid drain troughs.
- Excavate and install 24 vaults 12’ x 12’ x 10’ deep
- Restore 300 LF of Curb & Gutter and 2,600 SF of Sidewalk.
Original Bid Amount: $492,718.00
Change Orders: $307,000.00 – to date
Claims: $ ---0---
Final Contract Value: $ 799,718.00 – to date
Original Start Date: September 2011
Original Duration:
Original Completion Date: August 2014
Time Extension Granted In Days: TBD
Actual Completion Date: TBD – For C-QC work
Liquidated Damages: None
Recordable Accidents/ RAF: Zero / 0
Lost Time Accidents/ LAF: Zero / 0
OSHA Violations/ Fines: None
Project Name: Northeast Corridor Lumberjack Curve Realignment
Location: Sacramento, CA
Owner: Sacramento Regional Transit District
Owner Contact: Gregory Austin
Prime Contractor: Granite Construction Company
Prime Contractor: Contact Steve DeBlasio – 408.327.7000
Architect/Engineer: Owner
Architect/Engineer Contact: N/A
Construction Manger Contact: N/A
Description Of Project Scope: Civil Support and Trenching for Electrical/Signal contractor. Work performed around live tracks in a congested downtown atmosphere.Excavated and restored 6,605 LF of trench, including 8 track crossings under live LRT traffic. Drilled and Poured 13 OCS Pole Foundations.
Original Bid Amount: $409,500
Change Orders: $530.87
Claims: $ ---0---
Final Contract Value: $410,030.87
Original Start Date: April, 2009
Original Duration: Sub – Worked within Primes Schedule
Original Completion Date: N/A
Time Extension Granted In Days: N/A
Actual Completion Date: October 29, 2009
Liquidated Damages: None
Recordable Accidents/ RAF: Zero / 0
Lost Time Accidents/ LAF: Zero / 0
OSHA Violations/ Fines: None
Project Name: 5 Fulton Ductbank Construction Project MR-1242
Location: San Francisco, CA
Owner: San Francisco Municipal Transportation Agency
Owner Contact: Victor Yuen 415-706-1142
Prime Contractor: Con-Quest Contractors, Inc.
Prime Contractor Contact: N/A
Architect/Engineer: N/A
Architect/Engineer Contact: N/A
Construction Manger Contact: N/A
Description Of Project Scope: Installed 7,325 LF of 2 -2” & 6 – 6” HDPE concrete encased ductbank. Exc, Set and Backfilled 15- 6’ x 8’ x 8’ vaults for Traction Power System along Fulton Street between 32nd and 8th Avenues. Install 2,670 LF of GRS conduit to new and existing Feeder Trolley Poles. Install 12 new trolley poles & foundations. Modify existing overhead contact system.Install 1425 CY of new concrete street base; ground 103,680 SF of existing asphalt; and, place 1,605 tons of new asphalt. Install 1,700 SF of sidewalk; 400 LF of curb & gutter; and, 19 curb ramps.
Original Bid Amount: $ 6,053,975.00
Change Orders $ - 550,000.00
Claims $ ---0---
Final Contract Value: $ 5,453,975.00
Original Start Date: January, 2011
Original Duration: 485 Calendar Days
Original Completion Date: May, 2012
Time Extension Granted In Days: N/A
Actual Completion Date: January, 2012
Liquidated Damages None
Recordable Accidents/ RAF Zero / 0
Lost Time Accidents/ LAF Zero / 0
OSHA Violations/ Fines: None
Project Name: Port of Oakland Shore Power
Location: Oakland, CA
Owner: Port of Oakland
Owner Contact:
Prime Contractor: Blocka Construction, Inc.
Prime Contractor: Contact Brian Young – 510.377.8901
Architect/Engineer:
Architect/Engineer Contact: N/A
Construction Manger Contact: N/A
Description Of Project Scope: Civil support for Blocka Construction to install 400 lf of ductbank, excavate and set a power vault and form/pour CIP generator pad.
Original Bid Amount: $ 84,000.00
Change Orders: $TBD
Claims: $ ---0---
Final Contract Value: $TBD
Original Start Date: January 2012
Original Duration:
Original Completion Date: TBD
Time Extension Granted In Days: TBD
Actual Completion Date: TBD – For C-QC work
Liquidated Damages: None
Recordable Accidents/ RAF: Zero / 0
Lost Time Accidents/ LAF: Zero / 0
OSHA Violations/ Fines: None